A1.3

A1.3
The entity tests recovery plan procedures supporting system recovery to meet its objectives.
Category
Availability
Subcategory
Additional Criteria for Availability

Points of Focus​

Implements Business Continuity Plan Testing

Business continuity plan testing is performed on a periodic basis to test the entity's ability to respond, recover from, and resume operations through significant disruptions. Testing includes (1) development of testing scenarios based on threat likelihood and magnitude; (2) consideration of system components from across the entity and vendors that can impair availability; (3) scenarios that consider the potential for the lack of availability of key personnel or vendors; and (4) revision of continuity plans and systems based on test results.

Tests Integrity and Completeness of Back-Up Data

The integrity and completeness of back-up information is tested on a periodic basis.

Evidence Requests​

Area of FocusArtifactDescription
Business ContinuityContinuity of Operations Plan (COOP) TestingDocumented evidence of a COOP-related testing activity.
Business ContinuityCOOP TrainingDocumented evidence of a COOP-related training activity.

Policies​

Example Organization Controls​

  • A1.3.1 - A business continuity plan is documented and outlines the range of disaster scenarios and steps that the business will take to ensure the resumption of critical business operations.
  • A1.3.2 - Backup systems are in place to perform scheduled backups of production databases at predefined times.
  • A1.3.3 - Data backup restoration tests are performed at least annually.

Example Control Objectives​

  • Data recovery capability - Data backup and recovery procedures ensure timely restoration of services.

Example Control Implementations​

  • database-backup-recovery - Database backups are automated with point-in-time recovery capability. Implementation includes: - Cloud SQL automated backups with 30-day retention - Point-in-time recovery enabled for production database - Backups stored in GCS with encryption - Annual DR test validates recovery procedures - recovery time objective (RTO): 4 hours, recovery point objective (RPO): 1 hour

Example Evidence​

  • Backup Restoration Test Results - Documentation of quarterly backup restoration test including time measurements and verification steps
  • Disaster Recovery Test Report - Annual DR test documentation including scenario, results, and lessons learned

Example Action Plans​

  • Annual disaster recovery test - Annual full disaster recovery test to validate RTO/RPO objectives and recovery procedures. Tests database restore, application deployment, and failover capabilities.

Example Remediations​

  • backup-verification-remediation - Conduct and document quarterly backup restore tests to verify data recovery capabilities meet RTO/RPO objectives.